What is the Capital Improvement Plan and how is it created?

Mesa County's Capital Improvement Plan (CIP) is a 6-year plan for prioritizing and funding the County's infrastructure, property, facility, equipment, and technology needs. Most capital expenditures are budgeted in the Capital Fund, which receives dedicated revenue from the County's 2% sales tax. County staff consider a number of factors in determining which projects to include in the CIP, including user health and safety, the capacity of existing assets, funding availability, and legal requirements.

Because the Board of County Commissioners makes appropriations on an annual basis, projects and amounts identified in the 6-year CIP beyond the budget year are estimates only and remain subject to change. In appropriating budget, the Board sets the legal limit on total spending within each fund. Thus, actual expenditures for specific projects may exceed budget estimates, as long as total expenditures within the Capital Fund remain within the established appropriation.

6-Year CIP by Project Type

Explore the data below to learn more about the allocation of capital project funding across different departments and types of projects: Public Works, Facilities, Information Technology, Regional Transportation Planning, and Other Projects & Expenditures.

Public Works

Public Works projects involve the construction, maintenance, repair, and enhancement of County-owned infrastructure, including roads and bridges, sidewalks, wastewater treatment systems, and curbs and gutters. Transportation and other public infrastructure projects budgeted in 2026 and projected in 2027-2031.

  2026 Budget 2027 Budget 2028 Budget 2029 Budget 2030 Budget 2031 Budget
Joint Municipal Projects $500,000 $500,000 $500,000 $500,000 $500,000 $500,000
Rural Road Safety 250,000 200,000 750,000 0 750,000 0
Quality Assurance 100,000 100,000 150,000 150,000 150,000 150,000
Traffic Safety 200,000 200,000 200,000 200,000 200,000 200,000
C 1/2 Rd Overlay 500,000 0 0 0 0 0
On Call Engineering 250,000 250,000 400,000 400,000 400,000 400,000
Multimodal - Misc           3,000,000
Riverfront Trail 0 625,000 0 0 0 0
E Road 0 5,000,000 0 0 0 0
Orchard Ave 7,600,000 2,600,000 8,500,000 0 7,000,000 0
32 1/2 Road Corridor 5,500,000 0 0 0 0 0
38 Rd Bike & Ped 6,900,000 0 0 0 0 0
31 1/2 & E Rds to I-70B 1,000,000 0 0 5,000,000 0 0
F 1/4 Rd, 32 Rd, to I-70B 0 0 0 600,000 3,000,000 0
17 Rd, K 3/4 Rd, to W Sunset Dr. 0 0 0 300,000 1,500,000 0
Road Rehab- Misc 0 0 0 0 0 1,000,000
Coffman Rd 0 3,000,000 0 4,000,000 0 0
Overlay 3,500,000 4,500,000 7,500,000 8,000,000 8,000,000 8,000,000
On Call Concrete 200,000 200,000 200,000 200,000 200,000 200,000
Vega Rd Rehab 2,500,000 2,000,000 0 0 0 0
Bookcliff Ave, McMullin Dr 0 750,000 0 0 0 0
30 Rd, A 1/2 Rd to B 1/2 Rd 0 0 0 300,000 0 1,500,000
I Rd, east of 25 Rd 500,000 0 0 0 0 0
B 1/2 Rd, 30 Rd to 32 Rd 0 0 1,000,000 0 0 0
29 Rd Interchange 250,000 2,000,000 500,000 500,000 0 0
Stormwater 1,000,000 1,000,000 1,000,000 1,000,000 1,000,000 1,000,000
Bridges & Structures 0 0 1,000,000 1,000,000 3,000,000 3,000,000
Inspections 0 150,000 100,000 100,000 0 0
Pipe 600,000 450,000 600,000 600,000 700,000 600,000
Mesa Q-6.8 Bridge Rehab 4,500,000 0 0 0 0 0
MM-14-O.4 Minor Structure D/B 0 500,000 0 1,000,000 0 0
MM-14.5-O.4 Minor Structure 0 0 500,000 1,000,000 0 0
MM-M-14.2 & 14.37 Minor Structure 0 0 0 500,000 2,000,000 0
GPS 100,000 150,000 150,000 150,000 150,000 150,000
Asset Management 400,000 400,000 250,000 0 0 250,000
Mack Lagoons 0 300,000 2,500,000 0 0 0
Other Project 1,616,193 1,664,679 1,714,619 1,766,058 1,819,039 1,873,611
Total $37,966,193 $29,239,679 $27,514,619 $27,266,058 $30,369,039 $21,823,611

 

Facilities

Facilities projects involve the acquisition, construction, maintenance, repair, and enhancement of County-owned land and buildings. Budgeted projects in 2026 and projected projects in 2027-2031 related to the upkeep, repair, enhancement, and development of County property.

  2026 Budget 2027 Budget 2028 Budget 2029 Budget 2030 Budget 2031 Budget
Justice Center 0 0 0 0 0 1,500,000
Justice Center North Addition 3,797,588 0 0 0 0 0
Asset Preservation 1,808,077 2,002,000 2,775,000 2,610,000 1,950,000 1,775,000
Clifton Campus Maint. Shed 450,000          
HVAC Replacements 3,775,000 2,000,000 1,250,000 1,250,000 975,000 200,000
Other Projects 381,094 403,960 428,197 453,889 481,122 509,990
Total $10,211,759 $4,405,960 $4,453,197 $4,313,889 $3,406,122 $3,984,990

 

Information Technology

Information Technology (IT) projects involve the acquisition and enhancement of computer hardware and other telecommunication devices and systems and the purchase, licensing, and servicing of major software applications. Software, hardware, and other technology projects budgeted in 2026 and projected in 2027-2031.

 

  2026 Budget 2027 Budget 2028 Budget 2029 Budget 2030 Budget 2031 Budget

PC Upgrades

275,000 450,000 450,000 450,000 450,000 450,000

Network/Infrastructure

400,000 400,000 400,000 400,000 400,000 400,000

Applications & E-Systems

276,250 200,000 200,000 200,000 200,000 200,000

Equipment Lease

162,000 162,000 162,000 162,000 162,000 162,000

Clerk Elections Equipment & Software

102,039 104,080 106,161 108,284 108,284 108,284

Telephone

60,000 60,000 60,000 60,000 60,000 60,000

Security Cameras

50,000 50,000 50,000 50,000 50,000 50,000

Uninterruptible Power Supply

0 0 75,000 0 75,000 0
GIS 100,000 175,000 0 175,000 0 175,000
Tyler Enterprise 823,750 0 0 0 0 0
Workday build/maintenance 400,000 0 0 0 0 0
CJS Software 1,000,000 0 0 0 0 0
NO PROJECT 1,210,036 1,282,638 1,359,596 1,441,172 1,527,643 1,619,301
Total $4,859,078 $2,883,718 $2,862,757 $3,046,456 $3,032,927 $3,224,585

 

Regional Transportation Planning

Regional Transportation Planning Office (RTPO) projects involve the study, design, and development of transportation system master plans in coordination with municipalities; the development of multi-modal transportation options; and Grand Valley Transit bus replacement. Transportation planning and design and public transit enhancement projects budgeted in 2026 and projected in 2027-2031.

  2026 Budget 2027 Budget 2028 Budget 2029 Budget 2030 Budget 2031 Budget

Grand Valley Transit Capital Projects

3,304,694 892,245 915,710 1,336,704 2,295,526 4,491,036
Other Projects 74,000 0 0 0 0 0
Total $3,378,694 $892,245 $915,710 $1,336,704 $2,295,526 $4,491,036

 

 

Other Capital Projects & Expenditures

Other projects and expenditures regularly include:

  • certain equipment purchases and motor vehicle leases in the Sheriff's Office;
  • transfers out of the Capital Fund to other County funds, primarily for debt service, Stormwater programming, and support for Mesa County's public improvement districts;
  • the purchase and replacement of fleet vehicles and heavy equipment by Fleet Management;
  • grants to local organizations for the purpose of economic development; and,
  • contingency funds to cover unanticipated or emergency expenses during the year.

Other capital projects and miscellaneous expenditures in the Capital Fund budgeted in 2026 and projected in 2027-2031.

 

  2026 Budget 2027 Budget 2028 Budget 2029 Budget 2030 Budget 2031 Budget
Sheriff 833,542 1,081,935 1,067,013 768,019 795,327 795,330

Fleet

2,391,411 2,391,411 2,391,411 2,391,411 2,391,411 2,391,411

Support Services & Transfers

3,547,589 6,374,657 3,378,057 1,374,657 1,374,657 157,857
Other Projects 1,146,000 576,000 576,000 894,000 1,465,500 1,476,405
Total $7,918,542 $10,424,003 $7,412,481 $5,428,481 $6,026,895 $4,821,003