Phase two of the 32 1/2 Road and Clifton Campus Roadway Improvement Project to begin
The second phase of the 32 1/2 Road and Clifton Campus Roadway Improvement Project begins on July 1, 2025, causing a closure of the Intersection of E Road and 32 1⁄2 Road until phase two of the project is complete.
Once completed, the project will bring crucial infrastructure upgrades to the Clifton area, enhancing safety and accessibility.
Travel & Other Impacts for Phase 2
E Road will be closed to all through traffic from 32 1⁄2 Road to 33 Road. Please use the marked detour routes.
Project Schedule for Phase 2
The project will be in operation Monday through Friday from 7 a.m. to 6 p.m.
The whole project scope includes:
- Phase 1: Crews will replace the bridge over the Grand Valley Irrigation Canal on 32 ½ Road, just south of Friendship Drive.
- Phase 2: A new roundabout and roadway extension will be constructed at the intersection of E Road and 32 ½ Road, connecting to the south end of 32 ½ Road near D 7/8 Road.
- Phase 3: D ¾ Road will be widened between East Chukar Way and West Chukar Way to a full residential road. A new sidewalk will link Rocky Mountain Elementary Park to the existing sidewalk west of Mountain Vista Drive.
Phase three of the project will soon get underway.
The project is anticipated to be completed in October 2025.
Please stay tuned for updates on the project's status. You can call the project hotline at 970-549-9611 or email 32.5rdcliftoncampusproject@gmail.com with any questions about the improvement project.